2024

May 2024: Advertised for Bid

The project was released for bidding, inviting contractor proposals for construction of runway, lighting, and associated NAVAID improvements.

May

Fall 2024: FAA Grant Award

Merrill Field Airport accepted the FAA Grant in September 2024.

Sep
2025

June 2025: Notice to Proceed Issued

Official Notice to Proceed initiated the start of construction activities for Runway 07/25 rehabilitation.

Jun

June-August 2025: Runway Closure

Runway 07/25 was fully closed for 60 days while crews completed milling, paving, lighting upgrades, NAVAID improvements, and final striping. This continuous closure enabled efficient completion of all airfield work.

Jun

September-November 2025: Project Closeout and Final Documentation

Punchlist items, final NAVAID work, and final inspections are anticipated.

Sep

Late 2025: Project Closeout

All construction packages will be finalized, and documentation will be completed to close out the Merrill Field Improvement Project.

Dec